DC EV Charger Installation
Steps:
1.Lift the charger with the forklift at the bottom slots or raise it up with eyebolts at the top.
2.Place the charger onto the concrete base of the final location against the holes at the bottom of the charger.
3.Fix with 4 screws against the expansion studs at bottom of the charger.
Holes (in red) at the bottom of the charger
Unit:mm
Wiring:
|
•Make sure the main switch wiring (MCCB or fuses) of the AC power supply are cutting the electricity supply during installation. •Have a qualified electrician perform power distribution operations. •Ensure that all electrical components are in good condition. |
|
Note: 1. The AC input cable is selected according to Current Regulations according to the maxim DC Charger output power configuration (120kW), nominal site AC voltage and AC distribution cable overcurrent protection device. 2.The site AC distribution shall be equipped with protection devices against AC cable overcurrent, short circuit and lightning strike. The AC distribution overcurrent protection device rating shall not be less than 1.5~2 times the actual DC Charger input power rating. |
Steps:
1. Lead the AC power cord into the bottom of the charging pile from the cable entry hole reserved on the cement base
2. Use a hole diameter of 10.5mm metallic electric terminal aligned with the required cable cross section according with the power of the Charge Point (60kW DC).
3. Use the M10 screw and washer provided in order to connect the electric terminals.
4. Check all safety labels are correctly placed. Close the Charger’s door. The Charger has a security switch (anti-tamper protection) installed that will avoid any charging session if the doors are opened.
|
Note: The three-phase L1, L2, L3 wiring sequence must be consistent with the electricity standard of the located country. Otherwise it will case some equipment inside display failure/alarm. |
5. Fix 2 metal panels at the charger bottom. Fasten with screws.
CHARGING MODULE INSTALLATION
Steps: 1. Internal side lock pulls outside to open ventilation covers on the both side of the charger. 2. Install the charging modules into the slots which have the same address mXXX as the modules, see the right figure. 3. Tighten the modules with the screws on both sides. 4. Place the ventilation cover back and fix to the cabinet. 5.Charger module address dialing
|
|
|
Note: When power on the charger, please double check the displayed dialing address is consistent with the label attached to the module. See the address in above figure for more info. |
4G wireless router/modem connection
The system has been installed the controller (TCU) which can support the 3G/4G Wireless communication. Customers can insert the local SIM card and 3G/4G network card into the controller to activate this function. The wireless 3G/4G communication needs to be set and configured according the local telecom operator environment.
Power on the charger
Steps: 1.Switch on the MCCB to power on AC input. Check whether the voltage is normal with multimeter. 2.Switch on the Lightning Protector Breaker. 3.Switch on System Power Supply Breaker. Check whether the voltage is normal with multimeter 4.Check whether all the beacons are illuminated in green, the screen display is . |
|